CRE 0.345 −2.8% GNG 0.100 +0.0% XTG 2.62 −0.8% LIFT 2.90 +1.1% ANK 0.325 −4.4% FIN 0.105 +0.0% BTO 7.17 +1.6% SGD 17.05 −0.8% CNC 1.55 −1.0% EFR 20.45 −0.7% UTWO 0.350 +0.0% LVX 0.540 +1.9% BONE 0.035 +0.0% CLCH 1.13 +0.9% DRY 0.305 +0.0% PUMA 0.130 +0.0% CRE 0.345 −2.8% GNG 0.100 +0.0% XTG 2.62 −0.8% LIFT 2.90 +1.1% ANK 0.325 −4.4% FIN 0.105 +0.0% BTO 7.17 +1.6% SGD 17.05 −0.8% CNC 1.55 −1.0% EFR 20.45 −0.7% UTWO 0.350 +0.0% LVX 0.540 +1.9% BONE 0.035 +0.0% CLCH 1.13 +0.9% DRY 0.305 +0.0% PUMA 0.130 +0.0%
Drill Results

Amaroq talks production operations at Nalunaq

AMRQ · Price

Executive Summary

  • Production at the Nalunaq gold mine is running ahead of expectations, with ~5,000 oz produced to 7 Oct 2025 and throughput on track for a 300 t/d nameplate by year‑end.
  • A planned four‑week shutdown in October will complete Phase 1 (gravity circuit automation) and allow Phase 2 construction (flotation circuit) to restart in Dec 2025, targeting completion by Q1 2026.
  • 2025 exploration programs (surface & underground drilling at Nalunaq, the 4,804‑m Nanoq drill, satellite gold, copper and critical metals work) are finished or underway, with assay results expected in Q4 2025 and a resource update slated for Q1 2026.

Key Details

  • Operations – Production:
  • Gold output to 7 Oct 2025 ≈ 5,000 oz, matching revised full‑year 2025 guidance.
  • Double‑shift processing plant implemented ahead of schedule in H2 2025.
  • Planned shutdown: third week of Oct 2025, ~4 weeks duration; will fully automate gravity circuit and finish major civil works (Phase 1).

  • Operations – Phase 2 Construction:

  • Installation of flotation circuit (civil works, piping, electrical, equipment) largely complete.
  • Remaining work to be performed inside plant after shutdown, restarting Dec 2025 and continuing through Q1 2026.

  • Throughput Goal:

  • Target nameplate throughput of 300 t/d by year‑end 2025.

  • Guidance Update:

  • Updated FY 2025 production guidance to be released after shutdown confirmation, coinciding with Q3 2025 results on 14 Nov 2025.

  • Exploration – Nalunaq South Deep (Surface):

  • Completed drilling ~250 m down‑dip of current resource; results pending for next mineral resource update (Q1 2026).

  • Exploration – Nalunaq Underground:

  • Drilling completed between 725–790 m levels; further definition drilling planned from 800 m upward.
  • Focus on high‑grade Main vein and parallel 75 vein.

  • Exploration – Nanoq Project:

  • 4,804 m drill program finished on schedule; core logging & sampling in progress, initial assay results expected Q4 2025.
  • Winterization of camp/equipment underway to enable earlier drilling start next year.

  • Satellite Exploration:

  • Gold, copper and critical metals programs completed; assays pending.

  • Strategic Site Visits:

  • Teams visited Black Angel and Kangerluarsuk projects for logistics and development pathway assessment; resampling program conducted.

  • Management Comment:

  • CEO Eldur Olafsson: “We are ahead of schedule across all key workstreams… I look forward to providing a full update on operations and outlook at our Q3 2025 results on Nov. 14, 2025.”

Notable Quotes

  • Eldur Olafsson, Chief Executive: “I am pleased with the progress the team and our commissioning crews and contractors have delivered to date. We are ahead of schedule across all key workstreams, a clear testament to the strength and capability of Amaroq's people.”
Read the original news release →