Northwire Canada EditionFriday, July 10, 2026
Northwire
TLO 5.37 +5.7% BNKR 4.88 +1.7% GG 2.25 +3.2% MJS 0.100 +5.3% PAAS 62.54 +3.6% PE 0.230 +0.0% SGML 17.19 +4.8% LAR 10.34 −1.1% NED 0.025 +0.0% GEN 0.080 +0.0% TVI 0.060 +0.0% SKYG 0.025 −37.5% WRLG 0.660 +6.5% FFU 0.120 −7.7% LOD 0.310 +3.3% CBI 0.110 +0.0% TLO 5.37 +5.7% BNKR 4.88 +1.7% GG 2.25 +3.2% MJS 0.100 +5.3% PAAS 62.54 +3.6% PE 0.230 +0.0% SGML 17.19 +4.8% LAR 10.34 −1.1% NED 0.025 +0.0% GEN 0.080 +0.0% TVI 0.060 +0.0% SKYG 0.025 −37.5% WRLG 0.660 +6.5% FFU 0.120 −7.7% LOD 0.310 +3.3% CBI 0.110 +0.0%
Production / Operations Neutral

Graphite One Provides FAST-41 Permitting Update For Graphite Creek Project

Graphite One Confirms Permitting Timeline Amidst Capital Gap Concerns

Executive Summary
  • Permitting Status: The Graphite Creek Project remains "in progress" under the U.S. Army Corps of Engineers following its acceptance as a FAST-41 covered project on June 2, 2025.
  • Timeline Confirmation: The company confirms it is adhering to the established 13.5-month schedule for federal environmental reviews and authorizations.
  • Projected Completion: The permitting process is projected to complete by September 29, 2026.
  • Future Expansion: Management intends to seek similar FAST-41 coverage for the planned advanced graphite manufacturing facility in Ohio.
  • Strategic Context: The update reinforces the supply chain strategy involving transport via the Port of Nome to lower 48 states and potential co-location with a recycling facility in Ohio.
Material Impact
  • Expectation vs. Reality: This news is largely consistent with previous announcements made in August 2025 regarding the FAST-41 timetable posting. It confirms no delays but does not introduce new milestones or final permit approvals.
  • Market Reaction Context: The stock has corrected significantly from its January 2026 highs ($2.52) to current levels (~$1.15), likely due to financing dilution and the gap between non-binding EXIM Letters of Interest (LoI) and actual construction capital requirements.
  • Materiality: The update is routine maintenance on a critical path item. While positive for operational certainty, it does not address the massive capital shortfall required to move from feasibility study to construction ($6.8B total CAPEX vs. recent $35M raise).
  • Risk Mitigation: It mitigates the risk of immediate permitting delays but leaves the financing risk unresolved. The Ohio facility FAST-41 pursuit is noted as "subject to project financing," highlighting that this permitting step is contingent on capital availability.
GPH · Price
Company Overview
  • Flagship Project: Graphite Creek Mine located ~60 km north of Nome, Alaska. Recognized by USGS as the largest graphite deposit in the U.S.
  • Feasibility Study Highlights (April 2025):
    • Capacity: 175,000 tpy graphite concentrate.
    • Mine Life: 20 years.
    • Post-tax IRR: 27%.
    • NPV: $5.03 billion (8% discount rate).
  • Supply Chain Strategy: Vertically integrated model mining in Alaska and processing into anode active material (AAM) in Warren, Ohio.
  • Rare Earth Elements: Independent testing confirms elevated Magnet and Heavy Rare Earths (HREEs) in garnet material (~85% of total REEs), positioning the deposit as a potential dual-product mine.
Read the original news release →

More from Graphite One Inc.