Production / Operations
Ucore talks U.S. rare-earth project, DPAS status

UCU · Price
Executive Summary
- Ucore Rare Metals provided a detailed progress update on its $22.4 million Phase II modification to the U.S. Army Contracting Command‑Orlando funding agreement for building a commercial RapidSX rare‑earth separation plant in Alexandria, Louisiana.
- The project has received Defense Priorities & Allocations System (DPAS) DO‑B8 rating, granting preferential treatment to related purchase orders under the Defense Production Act.
- Key engineering milestones have been reached: completion of initial fieldwork, >50 % progress on system‑engineering transition, and >75 % completion of long‑lead‑time material sourcing for a H2 2026 government demonstration.
Key Details
- Funding Agreement: $22.4 million U.S. modified funding agreement with the U.S. Army Contracting Command‑Orlando (Phase II modification dated July 9, 2025).
- DPAS Rating: DPAS DO‑B8 rating applied to purchase orders for the Louisiana SMC project, obligating suppliers to give these orders preferential treatment.
- Fieldwork Completed: Boundary surveys, Level II environmental site assessment, topographical and utility surveys, 3‑D building scan/Revit model, existing slab engineering analysis.
- Engineering Milestones:
-
50 % progress on system‑engineering transition from the Commercial Demonstration Facility (CDF) to the Louisiana SMC.
- Design engineering, material sourcing, and initial full‑scale RapidSX equipment confirmation testing underway.
- Feedstock Partnerships: In‑country due‑diligence meetings scheduled for August 2025 with prospective partners; definitive agreement discussions ongoing.
- Long‑Lead‑Time Materials (LLTM): >75 % of bill‑of‑materials and sourcing for primary and supporting LLTM equipment completed, targeting H2 2026 U.S. government demonstration of a single RapidSX machine.
- Project Objectives:
- Construct and demonstrate optimized full‑scale RapidSX modules at the CDF.
- Transfer technology to the Louisiana SMC using a systems‑engineering approach based on selected feedstocks.
- Install production capacity capable of processing hundreds of tonnes of heavy/light total rare‑earth oxide (TREO) per year.
- Future Capacity Plan: Upon successful Phase II completion, Ucore intends to install additional RapidSX machines to achieve a planned 2,000 tpa TREO Stage 1 construction and simultaneous production project.
- Investor Relations Engagement: Signed a prepaid cash agreement with ImpactDeck for $25,000 covering an initial six‑month term (Sept 15 2025 – Mar 15 2026) to enhance visibility and investor engagement.
Notable Quotes
“During the phase I government demonstration program, Ucore made significant strides in the validation and commercialization of its RapidSX separation technology platform,” said Mike Schrider, PE, Vice‑President & COO.
“The phase II full‑scale under‑way assembly and engineering transition work simply builds upon the approximately 5,500 hours of demonstration plant run time… allowing us to truly optimize the scaled‑up equipment.”
More from Ucore Rare Metals Inc.
Jul 07, 2026 · 08:58