WHN 0.375 −2.6% LME 0.140 +3.7% AAUC 30.49 +5.3% GGM 0.040 +14.3% FDY 6.18 +3.2% MOG 0.640 +3.2% NEXM 3.20 +1.3% NCAU 0.330 +3.1% LUC 0.160 +0.0% BTR 0.140 +0.0% SMRV 0.200 −16.7% BIG 0.880 +3.5% URC 3.89 +0.0% ATY 0.250 −2.0% NRM 0.075 +7.1% WMS 0.040 +0.0% WHN 0.375 −2.6% LME 0.140 +3.7% AAUC 30.49 +5.3% GGM 0.040 +14.3% FDY 6.18 +3.2% MOG 0.640 +3.2% NEXM 3.20 +1.3% NCAU 0.330 +3.1% LUC 0.160 +0.0% BTR 0.140 +0.0% SMRV 0.200 −16.7% BIG 0.880 +3.5% URC 3.89 +0.0% ATY 0.250 −2.0% NRM 0.075 +7.1% WMS 0.040 +0.0%
Drill Results

American Tungsten Provides Operational Update on Its IMA Mine Rehabilitation and Proposed Diamond Drill Program

TUNG · Price

Executive Summary

  • American Tungsten announced an expanded first‑phase diamond drilling program at the IMA Mine, increasing planned drill length from ~5,400 ft to >10,000 ft across five stations (D Level and Zero Level).
  • Rehabilitation work on access drifts at both D Level and Zero Level is progressing, with underground rig secured and a second drill rig procured; drilling is expected to start before the end of November.
  • The company highlighted recent non‑brokered LIFE financing closure and positioned itself to benefit from upcoming Chinese tungsten export controls, underscoring its strategic role as a domestic supplier.

Key Details

  • Financing: Recent successful close of a non‑brokered LIFE financing (details not disclosed) provides capital for the expanded drilling program.
  • Drilling Scope: Original drill program ~5,400 ft → now >10,000 ft; five planned stations (originally three) across D Level and Zero Level drifts.
  • Schedule: Double‑shift drilling schedule through year‑end; first‑phase drilling to commence before end of November 2025.
  • D Level Progress:
  • ~1,100 ft of underground access drift rehabilitated to initial cross‑cut location.
  • New access drift excavation ~25% complete (≈48 ft out of ≈138 ft remaining).
  • Underground drill rig secured on site.
  • Office and storage facilities established at canyon base; additional staff hired for core sampling/assaying.
  • Zero Level Progress:
  • Rehabilitation resumed to support two drill stations.
  • Access drift blockage (~125 ft from portal) being removed/re‑supported; work expected complete within two weeks.
  • Second diamond drill rig sourced and secured.
  • Infrastructure Additions: Improved access roads/switchbacks, full services installed, core shed being equipped, contracting Minetech USA, LLC for mine planning and geotechnical engineering.
  • Strategic Context: CEO Ali Haji notes accelerated drilling positions the company favorably for 2026 production and cites recent Chinese tungsten export controls (effective until 2027) as a market tailwind for domestic supply.

Notable Quotes

“Our team continues to lay a solid operational foundation for the IMA Mine ahead of our planned diamond drilling program in November… Accelerating our drilling program will put the company in a stronger position for its development and production efforts in the lead‑up to 2026.” – Ali Haji, CEO


Materiality Assessment: Material – Positive (expansion of drilling program and infrastructure upgrades represent a significant operational milestone that could materially affect future production and valuation).

Read the original news release →