Northwire Canada EditionSaturday, July 25, 2026
Northwire
B 0.150 +0.0% IFOS 2.28 −2.6% IMM 0.060 +0.0% ROCK 3.38 −1.7% NVX 0.250 −7.4% HAR 0.050 +0.0% YGT 0.175 +0.0% GEN 0.070 −nan% CRB 0.040 +14.3% MSA 7.07 +2.2% AEM 204.81 +0.7% OPW 0.105 +5.0% GRL 0.275 −1.8% AIS 0.150 +0.0% CUU 0.580 −1.7% SOMA 0.720 +5.9% B 0.150 +0.0% IFOS 2.28 −2.6% IMM 0.060 +0.0% ROCK 3.38 −1.7% NVX 0.250 −7.4% HAR 0.050 +0.0% YGT 0.175 +0.0% GEN 0.070 −nan% CRB 0.040 +14.3% MSA 7.07 +2.2% AEM 204.81 +0.7% OPW 0.105 +5.0% GRL 0.275 −1.8% AIS 0.150 +0.0% CUU 0.580 −1.7% SOMA 0.720 +5.9%
Technical Study

St. Augustine Announces Positive Results of the Kingking Copper-Gold Project Updated Preliminary Feasibility Study

SAU · Price

Executive Summary

  • St. Augustine Gold and Copper Ltd. released an updated PFS for the Kingking Cu‑Au project showing a post‑tax NPV of $4.18 billion and IRR of 34.2%, with a benefit‑cost ratio of 1.8.
  • The study confirms 960 Mt of mineral reserves (849 Mt milling, 111 Mt leaching) supporting 4.4 bn lb of payable copper and 6.9 mn oz of gold over a 38‑year mine life; first‑5‑year average production is 284 M lb Cu and 333,000 oz Au per year.
  • Capital estimate remains at $2.37 bn (initial) with a projected payback of 1.9 years, cash cost of $2.06/lb Cu (C1 $0.32/lb net of gold credits), and strong operating margins under base‑case metal prices.

Key Details

  • Economic Highlights
  • Post‑tax NPV @7%: $4.18 bn
  • After‑tax IRR: 34.2% (base case) – sensitivity up to 44.5% with +20% metal prices.
  • Benefit‑Cost Ratio (BCR): 1.8
  • Payback period: 1.9 years (initial capital).

  • Reserves & Resources

  • Proven & probable milling reserves: 849 Mt @ 0.26% Cu, 0.36 g/t Au.
  • Proven & probable leaching reserves: 111 Mt @ 0.23% Cu.
  • Total copper‑equivalent grade (first 5 yr): 0.83%; life‑of‑mine average 0.48%.

  • Production Forecast

  • First 5 years: 284 M lb (129 kt) Cu and 333,000 oz Au annually.
  • Life‑of‑mine total payable metal: 4.4 bn lb Cu (2.0 Mt) and 6.9 mn oz Au (214 t).

  • Capital & Operating Costs

  • Initial capital (incl. sustaining): $2.37 bn (base case); $2.85 bn under +20% CAPEX scenario.
  • Sustaining capital: $0.80 bn.
  • Total operating cost: $16.11/tonne ore (base).
  • C1 cash cost: $2.06/lb Cu, net of gold credits $0.32/lb Cu.

  • Metal Price Assumptions (Base)

  • Copper: $4.30 lb⁻¹
  • Gold: $2,150 oz⁻¹

  • Project Schedule

  • Year 1‑2: Mine development & heap‑leach construction.
  • Year 3: SX‑EW cathode production begins; mill construction completed.
  • Year 4: First copper concentrate and gold doré production.

  • Regulatory Status

  • Environmental Impact Statement (EIS) approved (2015); DMPF approved (2016).
  • ECC in good standing; ISO 14001‑2015 EMS certified (2018).
  • Mineral Processing Permit currently lapsed – renewal work underway.

  • Technical Advisors

  • PFS prepared by M3 Engineering & Technology Corp. (Tucson, AZ).
  • Reserve modeling and cost estimates by Independent Mining Consultants Inc. (IMC).

  • Opportunities for Further Optimization

  • Chloride leach of low‑grade sulfide stockpile to accelerate cash flow.
  • Grinding efficiency upgrades (high‑pressure grinding rolls).
  • Locked‑cycle flotation reagent optimization.

Notable Quotes

“The updated PFS is a long‑awaited milestone… The project will produce copper at one of the lowest rates worldwide and position Kingking among the top global producers.” – Michael G. Regino, COO

“Kingking is essentially shovel‑ready with permitting largely in place; we are now focused on moving to definitive feasibility.” – Nico Paraskevas, Executive Director

Read the original news release →

More from St. Augustine Gold and Copper Limited