Gold 3,881.40 −0.1% Silver 48.80 −2.5% Copper 6.06 −2.2% Oil 88.98 +0.3% Palladium 1,000.25 +0.9% BMR 0.165 +0.0% CLV 0.120 + VUL 0.360 −5.3% LUNR 15.67 −3.1% XTG 2.10 +5.0% RUA 1.06 −3.6% TUF 0.620 +0.0% NEXG 1.11 −2.6% ELEF 0.270 −3.6% LVG 0.345 +1.5% BBB 0.510 +2.0% NGC 0.055 −8.3% ABRA 10.46 −3.0% OBUL 0.345 +0.0% MKO 10.48 −3.1% SGML 7.45 +5.2% Gold 3,881.40 −0.1% Silver 48.80 −2.5% Copper 6.06 −2.2% Oil 88.98 +0.3% Palladium 1,000.25 +0.9% BMR 0.165 +0.0% CLV 0.120 + VUL 0.360 −5.3% LUNR 15.67 −3.1% XTG 2.10 +5.0% RUA 1.06 −3.6% TUF 0.620 +0.0% NEXG 1.11 −2.6% ELEF 0.270 −3.6% LVG 0.345 +1.5% BBB 0.510 +2.0% NGC 0.055 −8.3% ABRA 10.46 −3.0% OBUL 0.345 +0.0% MKO 10.48 −3.1% SGML 7.45 +5.2%
Production / Operations

Kiniero delivers first ore to mill and commences operations

RBX · Price

Executive Summary

  • First ore has been delivered to the Kiniéro mill, marking a key commissioning milestone for Robex’s Kiniéro Gold Project in Guinea.
  • The processing plant’s mechanical, electrical and instrumentation systems are performing as designed, keeping the project on schedule for a first gold pour in December 2025.
  • Ramp‑up to commercial production is targeted for Q1 2026, advancing Robex toward its goal of becoming a mid‑tier West African gold producer.

Key Details

  • First ore delivery: Initiated commissioning activities at the Kiniéro processing plant; photos released showing ore being off‑loaded.
  • Plant performance: Mechanical, electrical and instrumentation (MEI) systems are operating in accordance with design specifications and project expectations.
  • Production timeline: First gold pour remains on track for December 2025; commercial production ramp‑up planned for the first quarter of calendar year 2026.
  • Management comment: CEO Matthew Wilcox stated that delivering ore moves the project “a step closer to first gold” and reinforces confidence in meeting the projected schedule.
  • Project status: Commissioning progressing on schedule; no material delays reported.

Notable Quotes

“With delivery of first ore to the Kiniéro plant, we continue our commissioning activities while moving a step closer to first gold for the project, which we expect to pour this month.” – Matthew Wilcox, Managing Director and Chief Executive Officer, Robex Resources Inc.

Read the original news release →

More from Robex Resources Inc.