Production / Operations
Kiniero delivers first ore to mill and commences operations

RBX · Price
Executive Summary
- First ore has been delivered to the Kiniéro mill, marking a key commissioning milestone for Robex’s Kiniéro Gold Project in Guinea.
- The processing plant’s mechanical, electrical and instrumentation systems are performing as designed, keeping the project on schedule for a first gold pour in December 2025.
- Ramp‑up to commercial production is targeted for Q1 2026, advancing Robex toward its goal of becoming a mid‑tier West African gold producer.
Key Details
- First ore delivery: Initiated commissioning activities at the Kiniéro processing plant; photos released showing ore being off‑loaded.
- Plant performance: Mechanical, electrical and instrumentation (MEI) systems are operating in accordance with design specifications and project expectations.
- Production timeline: First gold pour remains on track for December 2025; commercial production ramp‑up planned for the first quarter of calendar year 2026.
- Management comment: CEO Matthew Wilcox stated that delivering ore moves the project “a step closer to first gold” and reinforces confidence in meeting the projected schedule.
- Project status: Commissioning progressing on schedule; no material delays reported.
Notable Quotes
“With delivery of first ore to the Kiniéro plant, we continue our commissioning activities while moving a step closer to first gold for the project, which we expect to pour this month.” – Matthew Wilcox, Managing Director and Chief Executive Officer, Robex Resources Inc.