Northwire Canada EditionWednesday, July 29, 2026
Northwire
CAN 0.055 +0.0% NVO 0.055 +0.0% ARIS 19.57 −4.2% IVN 10.59 −0.8% MCI 0.165 +0.0% MTS 0.130 +0.0% PPX 0.210 +0.0% ICON 0.030 −33.3% ACS 0.070 +0.0% EMPR 0.860 +2.4% CYG 0.140 +0.0% IZN 0.075 +25.0% XXIX 0.110 +0.0% MERG 0.815 −4.1% LEGY 0.910 +3.4% GTWO 9.19 −3.6% CAN 0.055 +0.0% NVO 0.055 +0.0% ARIS 19.57 −4.2% IVN 10.59 −0.8% MCI 0.165 +0.0% MTS 0.130 +0.0% PPX 0.210 +0.0% ICON 0.030 −33.3% ACS 0.070 +0.0% EMPR 0.860 +2.4% CYG 0.140 +0.0% IZN 0.075 +25.0% XXIX 0.110 +0.0% MERG 0.815 −4.1% LEGY 0.910 +3.4% GTWO 9.19 −3.6%
Technical Study

Namibia Critical Metals Inc. Announces Positive Pre-Feasibility Study for the Lofdal Heavy Rare Earths Project

NMI · Price

Executive Summary

  • Namibia Critical Metals released its Pre‑Feasibility Study for the Lofdal Heavy Rare Earths Project, presenting a Base Case NPV of US$389 M (pre‑tax) and IRR of 21.7%, and a Divergent Case NPV of US$1.25 B (pre‑tax) with IRR of 44.1%.
  • The study outlines total capital costs of US$347.9 M, pre‑production capex of US$273.4 M, and an after‑tax payback period of 4.2 years (Base Case) or 2.75 years (Divergent Case).
  • Mineral reserves are quantified at 32 Mt containing 56,341 t TREO (including 23,894 t LREO and 32,448 t HREO), supporting an average annual production of 1,478 t TREO (119 t Dy, 17.8 t Tb, 841 t Y).

Key Details

  • Economic Highlights
  • Base Case NPV (5% discount): US$389.2 M pre‑tax / US$275.5 M after‑tax.
  • Divergent Case NPV: US$1,245.6 M pre‑tax / US$747.9 M after‑tax.
  • IRR (pre‑tax): 21.7% (Base) vs 44.1% (Divergent).
  • After‑tax IRR: 19.0% (Base) vs 34.8% (Divergent).
  • Capital Payback (after‑tax): 4.2 yr (Base) / 2.75 yr (Divergent).

  • Capital & Operating Costs

  • Total capital cost: US$347.9 M (Mining US$27.6 M, Process US$181.6 M, Facilities US$58.7 M, Tailings US$21.6 M, Closure US$1.0 M, Contingency US$57.4 M).
  • Life‑of‑Mine operating cost: US$1.68 B total; US$96 per tonne mined; US$63.75 per kg TREO.

  • Production & Reserves

  • Proven & Probable reserves: 32.01 Mt at 0.075% TREO (56,341 t TREO).
  • Annual ROM feed: 3.01 Mt (1.10 Mt high‑grade + 1.91 Mt low‑grade).
  • Average annual output: 1,478 t TREO (119 t Dy, 17.8 t Tb, 841 t Y).

  • Metallurgical Findings

  • XRT sorting upgrades ROM by 2.3–2.7×; recoveries 60‑70% for low‑grade ore.
  • Flotation concentrate grade: 4‑6% TREO with overall recovery up to 70%; HREO recovery 58‑75%.
  • Pilot plant continuous flotation demonstrated 55.5% total REE recovery at 2.65% TREO grade.

  • Hydrometallurgical Flow Sheet

  • Simplified acid bake, two‑stage impurity removal, UIX, and dual‑stage HREE carbonate precipitation.
  • High‑temperature sulfation (600 °C) achieved 94% Tb/Dy dissolution; impurity removal reduced thorium, scandium, Fe, Al, U losses to ~2%.

  • Infrastructure & Utilities

  • Water supply: 1.5 M m³/yr required; borehole development cost US$10 M.
  • Power: 94,361 MWh/yr needed; grid + 33% solar; transmission line & substation capex US$29 M.

  • Pricing Assumptions (average life‑of‑mine)

  • Base Case: Dy $663/kg, Tb $2,880/kg, Y $60/kg.
  • Divergent Case: Dy $855/kg, Tb $3,712/kg, Y $130/kg.

  • Sensitivity Highlights

  • ±20% metal price change drives the largest NPV variation.
  • Metallurgical recovery variations (85‑115%) shift after‑tax NPV from ~US$100 M to ~US$440 M (Base) and from ~US$500 M to ~US$1 B (Divergent).

  • Joint Venture & Funding

  • JV with JOGMEC; JOGMEC has earned a 40% interest after C$10 M spend.
  • Total approved funding to date: C$17.445 M of the $20 M earn‑in requirement.

Notable Quotes

  • Darrin Campbell, President: “Lofdal is well positioned as one of very few advanced major Dy/Tb‑ and Y projects outside China… The Project's economic case is now underpinned by three value pillars: Dy/Tb high‑temperature magnet demand, Yttrium demand from aerospace, semiconductors and turbine industry and Nd/Pr magnet demand.”
Read the original news release →

More from Namibia Critical Metals Inc.