- Cleantek Industries confirms manufacturing of up to 60 HALO SE Crown Mount lighting systems is on schedule at its Crossfield, Alberta facility.
- First deliveries are expected in late Q2 2026 with continued shipments through Q3 2026.
- No anticipated impact from Middle‑East developments; the company remains aligned with its international contract commitments.
Key Details
- The HALO SE Crown Mount units are being produced for a previously announced international supply and installation contract.
- Manufacturing progress is proceeding as planned at the Crossfield facility.
- Delivery schedule: initial shipments slated for late Q2 2026, followed by ongoing deliveries through Q3 2026.
- Company monitoring geopolitical developments in the Middle East; currently no effect on delivery timeline.
- CEO Riley Taggart emphasized execution “exactly as planned” and highlighted the contract’s demonstration of Cleantek’s manufacturing scale capability.
Notable Quotes
“We are executing exactly as planned,” said Riley Taggart, CEO of Cleantek. “Manufacturing at our Crossfield facility is progressing on schedule, and we remain fully aligned with our delivery timeline.”